| AZ Tooling Standards Check-Off Sheet | ||||||
| Refer to www. azautomotive .com |
AZ Representative(s): | |||||
| Date of first evaluation: | ||||||
| Tool description: | ||||||
| Tooling Standards Reference |
OK | Variance allowed | ||||
| SECTION 1.0 GENERAL REQUIREMENTS: |
NG | N/A | x | |||
| 1.1.1. | Complies with references. | |||||
| 1.1.2. | Warrantee is defined by the statement of requirements. | |||||
| 1.1.5. | Operation manual available 15 days prior to installation at AZ? | |||||
| 1.1.6. | Cycle time based on statement of requirements. | |||||
| 1.2.1 | Have status reports been submitted to AZ weekly? | |||||
| 1.3.1. | Power, air volume, water and gas requirements provided to the AZ Manufacturing Engineer? | |||||
| 1.3.3. | Components on AZ approved standard components list? | |||||
| 1.3.5 | New drawing package is complete? | |||||
| 1.3.10. | Have drawings be updated to reflect all changes? | |||||
| 1.5.1. | Spare parts listing supplied to Manufacturing Engineer | |||||
| 1.6.1. | Breakdown (shipping) points ID. | |||||
| 1.6.2. | Air, water and oil lines drained and plugged before shipment. | |||||
| 1.7.1. | Guarding and protection provides adequate safety. | |||||